For the Latest News

U.S. Army Corps of Engineers Tulsa District News

Keystone Dam bridge replacement progressing nicely

Public Affairs
Published March 17, 2014
Gaping hole number one was the beginning of a replacement span of the roadway bridge over Keystone Lake Dam. This is the first of three spans removed. This will be repeated 18 times to replace roadway built over the dam structure in 1964. Completion of the replacement spans is expected by November 2014.

Gaping hole number one was the beginning of a replacement span of the roadway bridge over Keystone Lake Dam. This is the first of three spans removed. This will be repeated 18 times to replace roadway built over the dam structure in 1964. Completion of the replacement spans is expected by November 2014.

The Gantry crane shown here had to be custom built to fit the width of the roadway to remove the old roadbed sections and structural items. It will also be used to replace the 36x40 foot bridge spans with seven prefabricated 6x36 foot panel sections. The deck slab panels were built off site.

The Gantry crane shown here had to be custom built to fit the width of the roadway to remove the old roadbed sections and structural items. It will also be used to replace the 36x40 foot bridge spans with seven prefabricated 6x36 foot panel sections. The deck slab panels were built off site.

TULSA, Okla. — The Tulsa District Corps of Engineers report Kiewit Construction has removed eight of the 18 roadway spans over Keystone Dam. Modifications to the bridge piers are currently taking place. Next, the precast pier pedestals will be installed on the piers providing support for the new precast girders. 

Col. Richard Pratt, Commander of the Tulsa District said, “The progress on the Keystone Bridge replacement is impressive including the installation of a gantry crane used to remove the existing bridge components and replace them in a systematic and efficient manner."

After making necessary substructure repairs and upgrades, the spans will be replaced with prefabricated components custom made for the bridge. The purpose of using prefabricated components is to decrease the time of construction so the bridge can be reopened as soon as possible.

Project Engineer for the Corps Keith Rice said, “Removing the first span was used as a learning experience to improve efficiency and safety for removing the rest of the spans. The demolition is preceding placement of prefabricated roadway elements scheduled to begin this month.”

The 18 spans have been in place since the dam was constructed in 1964. Over time, the bridge has degraded to the point where engineers determined it necessary to replace the bridge.

Col. Pratt commented, "This project represents a great partnership between the U.S. Army Corps of Engineers and the Oklahoma Department of Transportation to replace a critical roadway crossing the Arkansas River just 15 miles west of Tulsa."

The complete replacement and opening of the roadway bridge is expected to be in November of 2014.  Contract completion is scheduled for February 2015.