Tulsa District Regulatory Permits for Public Comment

PURPOSE:  The purpose of these public notices are to inform you of a proposal for work in which you might be interested and to solicit your comments and information to better enable us to make a reasonable decision on factors affecting the public interest.

SECTION 10: The U.S. Army Corps of Engineers is directed by Congress through Section 10 of the Rivers and Harbors Act of 1899 (33 USC 403) to regulate all work or structures in or affecting the course, condition, or capacity of navigable waters of the United States.  The intent of this law is to protect the navigable capacity of waters important to interstate commerce.

SECTION 404: The U.S. Army Corps of Engineers is directed by Congress through Section 404 of the Clean Water Act (33 USC 1344) to regulate the discharges of dredged and fill material into all waters of the United States.  These waters include lakes, rivers, streams, mudflats, sandflats, sloughs, wet meadows, natural ponds, and wetlands adjacent to other waters.  The intent of the law is to protect these waters from the indiscriminate discharge of material capable of causing pollution and to restore and maintain their chemical, physical, and biological integrity.

U.S. Army Corps of Engineers, Tulsa District

Regulatory Office, Chief

918-669-7400

 

  • SWT-2011-860

    Expiration date: 12/21/2019

    This notice announces a proposed modification of the Terra Foundation In-Lieu Fee (ILF) Stream and Wetland Mitigation Program Instrument (August 2015) to add the Little River ILF project site (project site) within the Canadian C Service Area.

  • SWT-2017-339

    Expiration date: 12/17/2019

    The application is for an after-the-fact (ATF) permit for placement of fill material into an unnamed tributary of Arkansas River and also includes the placement of fill material for the proposed lateral AEL expansion of the existing , active solid waste landfill.

  • SWT-2019-317

    Expiration date: 12/7/2019

    The overall purpose of the work is to repair bank erosion that is encroaching and endangering the adjacent local road (E. 580 Road) and structures owned by the applicant. The project is intended to restore the stream bank within its historical limits and configuration of its normal meander channel and to provide bank stabilization and erosion protection. The project is not a water dependent activity and there are no special aquatic sites are located within the project site.

  • NATIONWIDE PERMIT (NWP) PRE-CONSTRUCTION NOTIFICATION (PCN) THE RELEASE OF FORM ENG 6082

    Certain NWPs require project proponents to notify Corps district engineers of their proposed activities prior to conducting the activities authorized by those NWPs, so that the district engineers can make case-specific determinations of NWP eligibility. The notification takes the form of a pre-construction notification (PCN). The purpose of a PCN is to give the district engineer an opportunity to review a proposed NWP activity to ensure that the proposed activity qualifies for NWP authorization. In most cases, the district engineer has 45 days after receipt of a complete PCN to determine whether the proposed activity qualifies for NWP authorization or requires another form of Corps authorization. More information on when an activity requires a PCN can be found in the Federal Register Notice: https://www.govinfo.gov/content/pkg/FR-2017-01-06/pdf/2016-31355.pdf
  • SWT-2019-538

    Expiration date: 11/7/2019

    The application is for an expansion of the Muscogee (Creek) Nation Casino parking lot. The applicant considers the expansion of the existing casino facilities as necessary to support operations on Indian Trust land .