USACE PROJECT NUMBER: SWT-0-14659
BACKGROUND:
The North Texas Municipal Water District (NTMWD) submitted an application June 4, 2008, to the USACE to discharge dredged and fill material into Bois d' Arc Creek in Fannin County, Texas for the construction of a dam to impound the flow of the creek to provide a new water supply reservoir. At the designed conservation pool of 534.0 ft msl, the lake would comprise 16,641 surface acres. This reservoir would provide water to numerous towns, cities, and utility districts in portions of Collin, Dallas, Denton, Fannin, Hunt, Kaufman, Rains and Rockwall Counties in north central Texas. At conservation pool the proposed reservoir will store 367,609 acre-feet and provide a firm yield of 126,200 acre-feet per year.
Bois d'Arc Creek is considered waters of the United States (U.S.), and the construction of a dam is an activity which requires authorization from the USACE subject to Section 404 of the Clean Water Act. Evaluation of the Section 404 permit application is a federal action subject to review under the National Environmental Policy Act of 1969 (NEPA). The USACE, Tulsa District has determined that the proposed project will require an Environmental Impact Statement (EIS) prior to the final decision on the permit application. The EIS is being prepared by a Third-Party Contractor, Mangi Environmental Group, at the direction of the USACE. As the EIS process unfolds, documents and announcements will be made available on this webpage.
Record of Decision and FEIS Errata Sheet
Department of the Army Record of Decision for the Standard Individual Permit Application for the Proposed Lower Bois d'Arc Creek Reservoir
FEIS Errata Sheet
Final Environmental Impact Statement and Appendices
Revised Draft Environmental Impact Statement and Appendices
LBCR Revised DEIS
|
March 2017 |
LBCR Revised DEIS cover title page and TOC
|
March 2017 |
LBCR Revised DEIS Appendix A, List of Persons and Agencies Consulted
|
March 2017
|
LBCR Revised DEIS Appendix B, Scoping Report
|
March 2017
|
LBCR Revised DEIS Appendix C, Revised Mitigation Plan Jan. 2017, Part 1
|
March 2017
|
LBCR Revised DEIS Appendix C, Revised Mitigation Plan Jan. 2017, Part 2
|
March 2017
|
LBCR Revised DEIS Appendix C, Revised Mitigation Plan Jan. 2017, Part 3
|
March 2017
|
LBCR Revised DEIS Appendix D, Reservoir Operation Plan
|
March 2017
|
LBCR Revised DEIS Appendix E - Clower economic studies
|
March 2017
|
LBCR Revised DEIS Appendix F-1, Signed TCEQ Water Use Permit for LBCR
|
March 2017
|
LBCR Revised DEIS Appendix F-2, tech memo - Water Availability Analysis
|
March 2017
|
LBCR Revised DEIS Appendix F-3, tech memo, Revised Water Availability Analysis
|
March 2017
|
LBCR Revised DEIS Appendix G, Cultural Resources Mgt. Programmatic Agreement
|
March 2017
|
LBCR Revised DEIS Appendix H-1, AJD for LBCR reservoir site
|
March 2017
|
LBCR Revised DEIS Appendix H-2, AJD for Riverby Ranch mitigation site
|
March 2017
|
LBCR Revised DEIS Appendix H-3, AJD for North WTP at Leonard
|
March 2017
|
LBCR Revised DEIS Appendix H-4, AJD for FM 1396 relocation -FM 897 Extension
|
March 2017
|
LBCR Revised DEIS Appendix I PDF for raw water pipeline, Part 1
|
March 2017
|
LBCR Revised DEIS Appendix I PDF for raw water pipeline, Part 2
|
March 2017
|
LBCR Revised DEIS Appendix I PDF for raw water pipeline, Part 3
|
March 2017
|
LBCR Revised DEIS Appendix I PDF for raw water pipeline, Part 4
|
March 2017
|
LBCR Revised DEIS Appendix J, HEP at reservoir site
|
March 2017
|
LBCR Revised DEIS Appendix K-1, Modifying the East TX HGM for LBCR Project
|
March 2017
|
LBCR Revised DEIS Appendix K-2, Functional Assessment of Forested Wetlands at LBCR using Mod...
|
March 2017
|
LBCR Revised DEIS Appendix L-1, Rapid Geomorphic Assessment of Bois d'Arc Creek, 2008
|
March 2017
|
LBCR Revised DEIS Appendix L-2, Supplemental RGA for LBCR, 2016
|
March 2017 |
LBCR Revised DEIS Appendix M-1, lnstream Flow Study, Part 1
|
March 2017
|
LBCR Revised DEIS Appendix M-1, lnstream Flow Study, Part 2
|
March 2017
|
LBCR Revised DEIS Appendix M-1, lnstream Flow Study, Part 3
|
March 2017
|
LBCR Revised DEIS Appendix M-2, Instream Flow Study Supplemental Data
|
March 2017
|
LBCR Revised DEIS Appendix N, NTMWD Water Supply Planning Process 3-11-17 PS
|
March 2017
|
LBCR Revised DEIS Appendix O, Alternatives Dismissed_3-11-17docx PS
|
March 2017
|
LBCR Revised DEIS Appendix P, NRCS Farmland Conversion Impact Rating Form
|
March 2017
|
LBCR Revised DEIS Appendix Q-1, Env Rpt Supporting an Application for a 404 Permit
|
March 2017
|
LBCR Revised DEIS Appendix Q-2, App. A to App. Q - PMF Report
|
March 2017
|
LBCR Revised DEIS Appendix R, Report Supporting Application for TX Water Right 2006
|
March 2017
|
LBCR Revised DEIS Appendix S Archeological Sites Identified in Surveys PS
(Contact Corps for Information)
|
March 2017
|
LBCR Revised DEIS Appendix T, LBCR Conceptual Clearing Plan
|
March 2017
|
Draft Environmental Impact Statement documents
Environmental Impact Statement documents
Public Notices and Announcements
Public Meetings
Public Scoping Meeting |
December 8, 2009 |
PERMIT APPLICANT: North Texas Municipal Water District